<img alt="" src="https://linkprotect.cudasvc.com/url?a=https%3a%2f%2fsecure.perceptive-innovation-ingenuity.com%2f793281.png&amp;c=E,1,cVWb3ONniAlDlNWF2yGLX1Pu2WoXcj4VdEZrGpVWBuy0HFnzdTmQ0092CBaaLP-9kb5fQu4aUpN7ArnPFHbGez75leEP_6roXWIL3Jw3iw,,&amp;typo=1" style="display:none;">
    Projects

    USFWS Midway Atoll Storage Facility

    placeholder-1140x400

    The Rundown
    The United States Fish and Wildlife Service requested a 7200 sq ft warehouse for year-round storage at the world's largest Albatross colony, the island of Midway Atoll.

    Industry

    Size

    7,200 sq ft

    Location

    Midway, Atoll

    Year

    2019

    Testimonials

    Legacy has superior installation value.

    Having designed the mechanical and electrical systems, as well as structural foundations for these types of buildings, we find that a Legacy fabric structure has superior insulation value compared to a pre-engineered metal structure with the same ‘R’ value of insulation.

    Terry Smith TWS President and CEO

    We had a great working relationship with Legacy

    A lot of the temporary structures in the region are fabric structures, so we mainly looked at those types of buildings. Due to the overall project timeline, the buildings had to be constructed in the dead of winter. We had a great working relationship with Legacy throughout the entire process. They supply a very high quality fabric structure, and we're certainly pleased with what we've seen from the buildings thus far.

    John Lehman BBE Hydro Constructors

    The Legacy construction crew was very professional and courteous.

    Because of our soil issues, we simply couldn't afford to construct a more traditional building. The concrete costs made a more traditional building cost prohibitive. The lightweight design of our Legacy building allowed us to reach a compromise between soil conditions and cost. Regarding the design and construction phases of the building, I can say that the process went exceptionally well. When I made eleventh-hour changes to the job, Legacy handled them with ease. They finished the job well ahead of schedule, worked safely, and followed our stringent safety requirements to the letter.

    Joe Bitter Alliant Energy/IEI Barge Services
    Golden accent arrow

    Start Your Project

    Partnerships Equal Structural Integrity

    Whatever your industry, project, and desired application, the Legacy team of engineers will make your vision a reality. Start your project with the team who will provide you more than the structural integrity of your building a partnership.